Working with Charts

Charts enable you to visualise objects and their attributes and relations in ADOIT. Large amounts of data are clearly displayed graphically and can be understood more easily.

Types of Charts​

There are six types of charts in ADOIT:

Analysis: Dataset and Charts Combined​

In ADOIT, you do not just create a chart, you create a comprehensive analysis. An analysis consists of a set of data and selected charts for visualisation. This means that you can easily create multiple charts from one data set. You can save an analysis for future use and even share it with your colleagues.

Create Beautiful Charts​

It's easy to create attractive charts in ADOIT. Here is what you need to do:

  1. Start by creating a new analysis.

    • Go to   Analyse and create a new analysis.

    • Define the dataset. You can either use a search result or select your dataset manually.

  2. When you are satisfied with the initial dataset for the analysis, you can add and configure charts to visualise your data.

    • Select the chart type you want from the   Chart button.

    • Configure the chart in the side panel to visualise your data. You can customize the chart according to your wishes or simply choose one of the recommended templates for your data.

    • Optionally, make objects in your chart coloured to highlight some aspects of your data.

Available Charts​

Let's take a look at the charts that you can create in ADOIT:

Bar​

Using a bar chart, you can represent data as bars which can be aggregated across different levels.

A typical use case is the representation of the lifecycle state of Application Components.

 Example of a Bar Chart

Box-in-Box​

A box-in-box chart shows dependencies between different objects. The objects are arranged as boxes nested within each other.

A typical example is the representation of the hierarchy of company-related Capabilities.

 Example of a Box-in-Box Chart

Bubble​

Using a bubble chart, you can visualise objects as bubbles in a two-dimensional grid. Two attributes represent the x and y axis and an optional third attribute can be used for the bubble size.

A possible use case is the evaluation of an application portfolio based on business fitness, cost fitness and strategic importance.

 Example of a Bubble Chart

Gantt​

Using a Gantt chart, you can display the chronological sequence of objects on a timeline. Two attributes determine the start and end date of a bar.

One possible use case is the visualisation of the lifecycles of applications which are depicted as horizontal bars together with a timeline.

 Example of a Gantt Chart

Matrix​

In a matrix chart, dependencies between objects can be displayed in tabular format. You can define object types for the columns and rows and visualise the connections between the objects in the cells.

One possible use case is the visualisation of the interfaces of applications. For example, the Application Components may be placed in the rows and the Application Interfaces in the columns, with the Composition relations between them placed in the cells.

 Example of a Matrix Chart

Radar​

Using a radar chart, you can visualise objects in a circular chart. Based on two attributes, the objects are categorised into segments and rings.

Each object appears as a 'blip' on the radar chart and is given a number that uniquely identifies it. The object names and the corresponding numbers are listed right below the chart.

A typical use case is the identification and assessment of technologies for new software development projects (technology radar).

note

You can view a tooltip with the name of the object and other information when you position the mouse pointer over a blip in the radar chart.

 Example of a Technology Radar

The Analyses Page​

The Analyses page serves as a starting point to run analyses on a data set of your choice. All analyses that have been created are listed here, and you can create new analyses.

 The Analyses Page

Open Analyses Page​

To open the Analyses page:

  • On the toolbar at the top of the screen, click   Analyse.
Create New Analysis​

See Create Analysis.

Open an Analysis​

All analyses are shown in a compact list, sorted by date of last change.

  • To open an analysis, click it.

Create Analysis​

Use one of the following options to create an analysis:

 Create Analysis Button

Use a Search Result​

To create an analysis based on a search result:

  1. On the toolbar at the top of the screen, click   Analyse.

  2. Click the   Create analysis button, and then select From search result. The new analysis opens, with the Dataset tab selected.

  3. Perform a search. This works the same as when using the regular search function in ADOIT.

The search result will be used as the basis for the analysis. Now you can add and configure charts to visualise your data.

Manually Select Dataset​

To create an analysis and manually select the dataset:

  1. On the toolbar at the top of the screen, click   Analyse.

  2. Click the   Create analysis button, and then select From manual selection. The new analysis opens, with the Dataset tab selected.

  3. Now do one of the following:

    • Drag the models and objects you want to add from the Explorer to the Dataset tab.

    • Click the   Add button. Select the models or objects you want to add, and then click OK.

When you are satisfied with the initial dataset for the analysis, you can add and configure charts to visualise your data.

Directly Create Charts​

You've already picked data while working with ADOIT (for example, in the Explorer) and wish to generate charts straight from this data? This is also possible. You can choose from the following options:

 Create Charts Button

  • From the Search Function: Perform a search using the regular search function. Click the   Create chart button, and then select a chart type.

  • Based on a Selection of Objects and Models: Select the models or objects for the chart, e.g. in the Explorer, in an editor or in a list. Right-click the selection, point to   Create chart, and then select a chart type.

  • For All Objects in a Model: Open the model with the objects you want to analyse in an editor of your choice. Click the More button at the top right corner of the model, point to   Create chart, and then select a chart type.

No matter which method you used to directly create a chart, the procedure now continues in the same way. The new analysis opens. As the data is already available, the chart tab will be selected. The centre panel showing the selected chart will yet be empty. Configure the chart in the side panel to visualise your data.

Add Charts​

To add a chart to your analysis:

  1. Click the   + Chart button, and then select a chart type. The chart opens in a new tab.

  2. In the side panel, go to the Options tab to configure the chart (either select a template or configure the chart manually):

  3. Optionally, in the side panel, go to the Colour   tab and make objects in a chart coloured to highlight some aspects of your data.

The chart will be displayed in the centre panel.

Configure Bar Chart​

A bar chart represents objects as bars. Each object is given a bar. Their length is defined by an attribute.

Bar charts must have at least one level. If they have multiple levels, only the objects of the lowest level are represented by bars. However, the values of the lowest level can be aggregated across different levels.

Example: Configure Bar Chart

The configuration of a simple bar chart could look like this:

 Example: Configure Bar Chart

  • Application Component, and the length of the bars is based on the Lifecycle state attribute.

    This bar chart visualises the lifecycle state of Application Components.

To configure a bar chart, use these options in the side panel on the Options tab:

Select Template​

To get a quick start on creating a bar chart, you can use a template:

  • From the    Check out the available templates for your dataset list, select the template you want.

The necessary options will be selected automatically. You can adjust them as needed.

note

Templates may produce charts with a specific, non-standard representation.

Add Elements​

To add the first level to a bar chart:

  • Click the   Select an element from the dataset button, and then choose an object type from the dataset.

At least this first level needs to be created.

note

If the dataset only contains one type of object, it will be pre-selected and you can omit this step.

Optionally, to create a hierarchical structure, you can add additional levels to a bar chart:

  • Select a level in the configuration, click the   Add button, and then choose an object type.

The relation that connects the object type to the previous level will be automatically selected by ADOIT.

note

You can always add new levels below a level. Only when the top level is selected can you add a level above it.

Adjust Elements​

Elements can be removed, relations between levels can be changed, and levels can be hidden.

  • Remove Element: Select a level in the configuration, and then click the Remove element button . The level will be removed from the bar chart. If the level has child levels, they will also be removed.

  • Change Relation: Select a level in the configuration, click the Select relation button , and then choose a relation. The relation that connects the object type to the previous level will be changed.

  • Hide Level: Select a level in the configuration, and then click the Hide level button . This button is a toggle. Click it again to show the level again.

Select Attribute for Bars​

Choose the attribute that determines the bar length:

  • From the Bar dimension list, select the attribute you want.
Which attributes can be selected?

You can select the following types of attributes:

  • Enumeration: Attributes that are an enumeration (= a predefined set of values you can choose from).

  • Number: Attributes that store integers or floating point numbers.

If the bar chart has multiple levels, you can only choose an attribute for the lowest level.

If the lowest level of the bar chart contains multiple object types, only attributes that are shared by all of them can be selected.

Choose Layout Options​

Choose layout options to determine what the bar chart will look like:

  • Reverse X-Axis: Invert the x-axis so that higher values will be shown on the left and lower values on the right.

  • Show Elements with Missing Data: Specify whether to show objects in the bar chart where at least one of the selected attributes does not have a value defined.

note

The layout option Reverse X-Axis is only available if the bar attribute is an enumeration.

The layout option Show Elements with Missing Data is only available if the bar chart has only one level AND the bar attribute is an enumeration.

Choose Aggregation Method​

If a bar chart has multiple levels, bars are normally only shown for the values of the lowest level. However, these values can be aggregated across different levels. The combined values are then displayed as additional bars in the higher levels.

To choose an aggregation method for a bar chart:

  • From the Aggregation method list, select the method for calculating the aggregated value:

    • Maximum: Shows the largest value.

    • Minimum: Shows the smallest value.

    • Average: Shows the arithmetic mean (= sum of all values divided by number).

    • Sum: All values are added up.

note

This option is only available if the bar attribute is a number.

Example: Aggregate Data

The configuration of a bar chart could look like this:

 Example: Aggregate Data

  • Business Process < Served by < Application Interface < Composed in < Application Component

    In the visualisation, the values of the first level are aggregated to the second level, and the values of the second level are then aggregated to the third level.

    The chosen aggregation method is Sum, meaning that all values are added up.

     Example: Aggregate Data

Configure Box-in-Box Chart​

A box-in-box chart shows objects of different levels as boxes nested within each other. You need to choose the object types that are used on each level of the box-in-box chart and the relations that connect the levels.

  • A box-in-box chart needs at least two levels.

  • Each level must contain at least one object type.

  • Neighbouring levels in a box-in-box chart are connected by relations.

  • The direction of the relation is shown as an arrow in the configuration.

Example: Box-in-Box Chart Configuration

The configuration of a simple box-in-box chart could look like this:

 Example: Box-in-Box Chart Configuration

  • Application Component > Realization > Application Service

    This box-in-box chart has two levels. The first level contains the object type Application Component. The second level contains the object type Application Service. The relation Realization connects the first level and the second level of the box-in-box chart. The direction is from the first level to the second.

To configure a box-in-box chart, use these options in the side panel on the Options tab:

Select Template​

To get a quick start on creating a box-in-box chart, you can use a template:

  • From the    Check out the available templates for your dataset list, select the template you want.

The necessary options will be selected automatically. You can adjust them as needed.

note

Templates may produce charts with a specific, non-standard representation.

Add Elements​

To add the first level to a box-in-box chart:

  • Click the   Select an element from the dataset button, and then choose an object type from the dataset.
note

If the dataset only contains one type of object, it will be pre-selected and you can omit this step.

To add additional levels to a box-in-box chart:

  • Select a level in the configuration, click the   Add button, and then choose an object type.

The relation that connects the object type to the previous level will be automatically selected by ADOIT.

note

You can always add new levels below a level. Only when the top level is selected can you add a level above it.

Select Relation​

To change the relation that connects an object type to the previous level:

  • Select a level in the configuration, click the Select relation button , and then choose a relation.
Remove Element​

To remove a level from the box-in-box chart:

  • Select a level in the configuration, and then click the Remove element button .

If the level has child levels, they will also be removed.

Hide Level​

You can hide levels to visualise relations between objects that are indirectly related to each other through another object.

To hide a level in the visualisation:

  • Select a level in the configuration, and then click the Hide level button . This button is a toggle. Click it again to show the level again.
Example: Hide Level

In the following configuration, the second level of the box-in-box chart is hidden:

 Example: Hide Level

  • Business Process < Serving < Application Component < Serving < System Software

    In the visualisation, the objects of the first level directly contain the children of the hidden level (= the objects of the third level).

  • The Business Processes contain the System Software elements.

  • The Application Components are not visualised at all.

     Example: Hide Level

Customise Layout​

You can specify how objects in a level which share the same parent object are positioned:

  • For each level, select the number of Boxes per row before a new row is started.
Example: Set Growth Direction

Growth direction for the second level of the box-in-box chart is set as follows:

 Example: Customise Layout

  • Horizontal, with 4 items per row

    In the visualisation, four objects are placed in the first row, and then a new row is started.

     Example: Customise Layout

Sort Objects​

By default, objects at each level of a box-in-box chart are sorted alphabetically by name (A to Z). If you prefer a different order, you can select an alternative attribute for sorting in the side panel on the Options tab:

  • From the Sort by list, choose the attribute you want to use for sorting.

You can sort by attributes that contain text or numbers.

Sorting Rules and Limitations

An attribute is only available for sorting if it exists in all object types used at different levels of the chart.

Only attributes with global values can be used for sorting. Attributes with model-specific values are not supported.

If two objects have the same value for the selected sorting attribute, they are sorted alphabetically by name as a fallback.

Configure Bubble Chart​

A bubble chart displays objects as bubbles on an area. The area is defined by two axes (x-axis and y-axis). Specify the type of objects to be displayed and the attributes for x-axis, y-axis and bubble size. The attribute for bubble size is optional; all bubbles have the same size when the attribute is not set.

Example: Configure Bubble Chart

The configuration of a simple bubble chart could look like this:

 Example: Configure Bubble Chart

  • Application Component, with the attributes Business fit for the x-axis and Cost fit for the y-axis.

    This bubble chart helps you assess the fitness of applications.

To configure a bubble chart, use these options in the side panel on the Options tab:

Select Template​

To get a quick start on creating a bubble chart, you can use a template:

  • From the    Check out the available templates for your dataset list, select the template you want.

The necessary options will be selected automatically. You can adjust them as needed.

note

Templates may produce charts with a specific, non-standard representation.

Select Object Type and Attributes​

Choose which object type and attributes will appear in the bubble chart:

  • Object Type: Specify what type of objects should be visualised in the bubble chart.

  • X-Axis: Choose the attribute you want to show on the x-axis.

  • Y-Axis: Choose the attribute you want to show on the y-axis.

  • Bubble Size: Choose the attribute which determines the bubble size.

Choose Layout Options​

Choose layout options to determine what the bubble chart will look like:

  • Reverse X-Axis: Invert the x-axis so that higher values will be shown on the left and lower values on the right.

  • Reverse Y-Axis: Invert the y-axis so that higher values will be shown on the bottom and lower values on the top.

  • Reverse Bubble Size: Invert the bubble size so that higher values mean a smaller size and lower values mean a bigger size.

  • Show Bubble Names: Specify whether the names of the objects should be displayed right next to the bubbles.

note

You can view a tooltip with the name of the object and other information when you position the mouse pointer over a bubble segment.

  • Show Elements with Missing Data: Specify whether to show objects in the bubble chart where at least one of the selected attributes does not have a value defined.

Configure Gantt Chart​

A Gantt chart shows objects as bars on a timeline. Choose which object types to display in the Gantt chart and which attributes to use for the start and end dates.

Example: Configure Gantt Chart

The configuration of a simple Gantt chart could look like this:

 Example: Configure Gantt Chart

  • Application Component, with the attributes Valid from and Valid until to visualise a time period.

    This Gantt chart visualises the lifetime of applications from the beginning to the end.

To configure a Gantt chart, use these options in the side panel on the Options tab:

Select Template​

To get a quick start on creating a Gantt chart, you can use a template:

  • From the    Check out the available templates for your dataset list, select the template you want.

The necessary options will be selected automatically. You can adjust them as needed.

note

Templates may produce charts with a specific, non-standard representation.

Add Elements​

To add the first level to a Gantt chart:

  • Click the   Select an element from the dataset button, and then choose an object type from the dataset.

At least this first level needs to be created.

note

If the dataset only contains one type of object, it will be pre-selected and you can omit this step.

Optionally, to create a hierarchical structure, you can add additional levels to a Gantt chart:

  • Select a level in the configuration, click the   Add button, and then choose an object type.

The relation that connects the object type to the previous level will be automatically selected by ADOIT.

note

You can always add new levels below a level. Only when the top level is selected can you add a level above it.

Select Relation​

To change the relation that connects an object type to the previous level:

  • Select a level in the configuration, click the Select relation button , and then choose a relation.
Remove Element​

To remove a level from the Gantt chart:

  • Select a level in the configuration, and then click the Remove element button .

If the level has child levels, they will also be removed.

Hide Level​

To hide a level in the visualisation:

  • Select a level in the configuration, and then click the Hide level button . This button is a toggle. Click it again to show the level again.
Example: Hide Level

In the following configuration the second level of the Gantt chart is hidden:

 Example: Hide Level

  • Application Component < Serving < Application Interface < Composition < Application Component

    In the visualisation, the interfaces between the applications are not visualised:

     Example: Hide Level

Select Start and End Attributes​

Choose which attributes will appear on the x-axis:

  • Select start: Select the attribute that represents the beginning of the bar along the timeline.

  • Select end: Select the attribute that represents the end of the bar along the timeline.

Configure Matrix Chart​

A matrix chart in ADOIT displays connections (matrix cells) between objects of the x-axis and objects of the y-axis. A connection can be:

  • a relation between x-axis object and y-axis object or

  • an object which is connected with the x-axis and y-axis objects by relations

You need to specify the type of objects to be displayed on the x-axis and y-axis, and the object type or relation for the matrix cells. If you want to choose an object type for the matrix cells, you must define how it is connected to the objects of the x-axis and y-axis.

Example: Configure Matrix Chart

The configuration of a simple matrix chart could look like this:

 Example: Configure Matrix Chart

  • Application ComponenApplication Interface > Composition > Application Interface

    This matrix chart shows the composition of interfaces as a table with Application Interfaces in the columns and Application Components in the rows.

To configure a matrix chart, use these options in the side panel on the Options tab:

Select Template​

To get a quick start on creating a matrix chart, you can use a template:

  • From the    Check out the available templates for your dataset list, select the template you want.

The necessary options will be selected automatically. You can adjust them as needed.

note

Templates may produce charts with a specific, non-standard representation.

Select Object Types and Relations​

Choose which object types and relations will appear in the matrix chart:

  • Rows: Choose the object types you want to show on the y-axis.

  • Cell: Select at least one relation that connects the objects of the x-axis and y-axis OR an object type and the relation that connects it to the objects of the y-axis. You can select multiple relations or object types.

  • Columns: Choose the object types you want to show on the x-axis. What needs to be selected depends on the type of connection chosen for the cells. If the connection is a relation, you can select an object type that is a valid source or target for the relation. If the connection is an object, you can select an object type AND a relation that connects it to the cell objects. You can configure multiple connections.

Choose Layout Options​

Choose layout options to determine what the matrix chart will look like:

  • Hide "No references" column: Specify whether to hide the "No references" column. This column is only available if objects are displayed in the cells. It lists all cell objects which are not connected to x-axis objects.

  • Hide "No references" row: Specify whether to hide the "No references" row. This row is only available if objects are displayed in the cells. It lists all cell objects which are not connected to y-axis objects.

  • Hide columns without cell objects: Specify whether empty columns should be shown in the matrix chart.

  • Hide rows without cell objects: Specify whether empty rows should be shown in the matrix chart.

  • Colour cells with multiple occurrences: Specify whether cell objects that occur multiple times in the matrix chart should be highlighted using slim vertical bars.

note

The layout options Hide "No references" column, Hide "No references" row and Colour cells with multiple occurrences are only relevant if objects are displayed in the matrix cells. They will be hidden if you select a relation for the matrix cells.

Configure Radar Chart​

A radar chart visualises objects in a circular chart. The chart is divided into segments and rings. Specify the type of objects to be displayed and the attributes for the segments and rings. Both attributes are optional, but at least one is required.

Example: Configure Radar Chart

The configuration of a simple radar chart could look like this:

 Example: Configure Radar Chart

  • System Software, with the attributes Adoption stage for the rings and Technology type for the segments.

    This radar chart is a technology radar. It helps you evaluate technologies for new software development projects.

To configure a radar chart, use these options in the side panel on the Options tab:

Select Template​

To get a quick start on creating a radar chart, you can use a template:

  • From the    Check out the available templates for your dataset list, select the template you want.

The necessary options will be selected automatically. You can adjust them as needed.

note

Templates may produce charts with a specific, non-standard representation.

Select Object Type and Attributes​

Choose which object type and attributes will appear in the radar chart:

  • Object Type: Specify what type of objects should be visualised in the radar chart.

  • Rings: Choose the attribute that defines the rings of the radar chart.

  • Segments: Choose the attribute that defines the segments of the radar chart.

Choose Layout Options​

Choose layout options to determine what the radar chart will look like:

  • Reverse Rings: Invert the position of the rings so that the inner rings will be shown on the outside and the outer rings on the inside.

  • Reverse Segments: Invert the position of the segments so that the segments are arranged counterclockwise instead of clockwise.

  • Show Elements with Missing Data: Specify whether to show objects in the radar chart where at least one of the selected attributes does not have a value defined.

  • Hide Legend: Specify whether to hide the legend displaying the object names and their corresponding numbers below the chart.

Apply Colouring to Charts​

You can make objects in a chart coloured depending on the value of an attribute to highlight some aspects of your data. For example, Application Components in a matrix chart could be coloured green if their strategic importance is high and red if their strategic importance is low.

To apply colouring to charts, use these options in the side panel on the Colour tab:

  • Enable Colouring: Click the Enable colouring button to enable colouring. All other options in this panel are inactive unless you click this button.

  • Select Element: Choose the object type you want to colour.

  • Select Attribute: Choose the attribute whose value determines how the objects will be coloured. If the attribute is an enumeration, you will immediately see the colour assignment to the values of the attribute. If the attribute represents a number or a date, you have to set values for colouring first (see below).

  • Reverse Colours: To invert the colour scheme, click the Reverse colours button .

  • Change Colours: To change colours, click the colour circles.

  • + Add Colouring: Click the + Add Colouring button to create an additional colouring rule for a different object type. When clicked, a new set of controls appears below the current set. You can add as many colouring rules as there are different object types. This allows you to colour multiple object types either according to the same attribute (if they share that attribute), or according to different attributes.

Set Values for Colouring​

The initial colour assignment to the values of the attribute will differ depending on the data type of the selected attribute.

  • Enumeration: If the selected attribute is an enumeration (= a predefined set of values you can choose from), then you don't need to do anything. Each value is automatically assigned a colour by ADOIT.

  • Number: For attributes that store integers or floating point numbers, you can define up to 5 different value ranges and assign them to a colour. Define the value range in the From and To fields. A colour will be preselected for each value range. You can add or remove value ranges by clicking the "+" and "x" icons.

  • Date: For attributes that store a date, you can define up to 5 different time periods and assign them to a colour. Define the period in the From and Until fields. You can either enter the start date and the end date manually or select them in the calendar. A colour will be preselected for each time period. You can add or remove time periods by clicking the "+" and "x" icons.

Delete Chart​

To delete a chart:

  • The More button is activated when you hover over the chart tab. Click this button to open a drop-down menu, and then click Delete.

View Dataset or Charts​

After creating an analysis, you can switch between viewing the dataset and the charts:

 View Dataset or Chart

  • Click the Dataset tab or the tab representing the chart you want to see.

Adjust Charts​

Charts can be refreshed, renamed, zoomed in or out, and more.

Refresh Chart​

To refresh a chart:

  • Click the More button at the top right corner of the chart, and then click Refresh  .
Rename Chart​

To rename a chart:

  • Click the More button at the top right corner of the chart, and then click Rename  .
Zoom in and out of a Chart​

To zoom in and out of a chart:

  • Click the icons or to increase or decrease the zoom value.

  • Click the icon to fit the chart to the window size.

Sort Objects​

You can sort a bar chart, a Gantt chart or a matrix chart to show objects in the order you want.

To sort objects alphabetically (A to Z or Z to A):

  • Click the up or down arrow next to Sort: Name at the top left corner of the chart.
note

Both rows and columns can be sorted in a matrix chart.

Manage Dataset​

Use the Dataset tab to view the current dataset and to choose the data you want to use.

 The Dataset Tab

Change Dataset Based on Search Result​

To change a dataset that is based on a search result:

  • Change the search string or the search options and filters.
Change Dataset Based on Manual Selection​

To change a dataset that is based on a manual selection, choose one of the following options:

  • Add Models or Objects to the Dataset: Drag the models and objects you want to add from the Explorer to the Dataset tab or:

    Click the   Add button. Select the models or objects you want to add, and then click OK.

  • Remove Models or Objects from the Dataset: Click the   Add button. Deselect the models or objects you want to remove, and then click OK.

Export Chart​

To export a single chart as an Excel spreadsheet (XLSX format), PDF or image file (SVG and PNG format):

  1. Open the chart you want to export.

  2. Click the More button , point to Export   , and then do one of the following:

    • Click Export image to export an image file. You can select the desired graphic options such as the image format (PNG or SVG) and the scale.

    • Click Print PDF to export a PDF. You can select the desired print settings such as the paper size and the orientation (portrait or landscape).

    • Click Export to Excel to export an Excel spreadsheet.

In all formats, the graphical representation of the chart and the legend are exported. Additionally, when exporting an Excel spreadsheet, the objects included in the chart are listed on a separate sheet.

Crop Image​

Before you export a chart as an image file, you can crop the image:

  • Press and hold <Ctrl>, <Shift> and the left mouse button and drag a frame around the part of the chart which shall appear in the graphic file.
note

In addition to exporting a single chart, you can also share the entire analysis with other users.

note

Due to technical limitations of the browser, when exporting a very large matrix chart as an Excel spreadsheet, the graphical representation may not be included.

Manage Templates​

Designated power users can save chart configurations as templates for future use and to make them available for others. They can also perform administrative tasks, such as renaming or deleting both user-created and predefined templates.

note

To manage templates and utilise the functions described below, a user must have access rights to the ADOIT Administration.

Create New Template​

To create a new template from a chart configuration:

  1. In the side panel on the Options tab, click Save template, and then click Save as new template.

  2. Enter a name and description for the template in every language ADOIT supports. At least the name in the primary language is required.

  3. Click Save.

A success message appears. Close the message to complete the process.

Save Modified Template​

To save a modified template after changing the chart configuration:

  • In the side panel on the Options tab, click Save template, and then click Update template.

  • When prompted to continue, click Save.

A success message appears. Close the message to complete the process.

Rename Template​

To change the name and description of a template:

  • In the side panel on the Options tab, below the template name, click Rename.

  • Modify the name and description as needed.

  • Click Save.

A success message appears. Close the message to complete the process.

Delete Template​

To delete a template:

  • In the side panel on the Options tab, below the template name, click Delete.

  • When prompted to continue, click Save.

A success message appears. Close the message to complete the process.

Charts with a Special Appearance​

Templates may produce charts with a specific, non-standard representation.

note

The availability of these templates depends on the Application Library and product configuration.

In the ArchiMate Application Library, the following charts with a special appearance are available:

Application Planning (Gantt)​

A changed visualisation is available for Gantt charts based on the following templates:

  • "Application Component Roadmap"

This visualisation shows the lifecycle of applications (Application Components) in great detail. Multiple attributes are displayed for each bar (= object). This allows you to see at a glance:

  • When the implementation of an application starts

  • When an application becomes productive

  • When an application is decommissioned

  • When an application replaces another

 An &quot;Application Component Roadmap&quot;

Technology Planning (Gantt)​

A changed visualisation is available for Gantt charts based on the following templates:

  • "System Software Roadmap"

This visualisation shows the lifecycle of technologies (System Software) in great detail. Multiple attributes are displayed for each bar (= object). This allows you to see at a glance:

  • When the implementation of a technology starts

  • When a technology becomes productive

  • When a technology is decommissioned

  • When a technology replaces another

Access (Matrix)​

A changed visualisation is available for matrix charts based on the following templates:

  • "Read-Write Matrix"

This visualisation shows how applications (Application Components) can act upon Business Objects. The following icons are used:

Read-Write Matrix​
  • Read: Application can read a business object

  • Write: Application can write a business object

  • Master: Application is considered as master of a business object

  • Violation: Application can write data without being the master of a business object

 A &quot;Read-Write Matrix&quot;

Save Analysis​

You can save an analysis (= specific data and selected charts) to view it again later and share it with other users. Analyses are stored in the Model Catalogue.

The following options are available:

Save​

To save changes to an analysis:

  1. Click the Save button in the menu bar of the analysis.

  2. Enter a name for the analysis and define a target group if you are saving it for the first time.

Save as​

To create a copy of the analysis with a new name:

  1. Click the down arrow symbol in the Save button .

  2. Select Save as   from the drop-down menu.

  3. Change the name of the analysis.

  4. Define the target group for the new analysis.

  5. Click OK.

note

If an analysis only allows read access, the Save button is replaced by the Save as button in the menu bar of the analysis.

Close Analysis​

To close an analysis:

  • Click the icon at the top right corner of the open analysis.

Find Analysis​

Here are some tips to find an analysis in ADOIT:

  • Model Catalogue: Analyses are stored in the Model Catalogue in the Explorer. You can browse the folders or use the search to find the analysis you're looking for.

  • Analyse   : In the "Design & Document" scenario, on the Analyses page, all analyses are shown in a compact list.

  • Architecture Diagrams: In the "Read & Explore" scenario, the Architecture Diagrams dashboard lists all analyses in the database.

Delete Analysis​

To delete an analysis:

  • Right-click the analysis in the Model Catalogue, and then click Delete.